New on GeoPrac.net, the Other News and Blogs page has had a major facelift. To supplement our regular GeoNews and Articles, we aggregate news feeds and blog entries from all over the web into one easy to browse source. Check it out!
Become an Author
GeoPrac.net is a community site, we are only as good as the content our members contribute!
Devils Slide is an infamous landslide along Californias Highway 1 or Pacific Coast Highway near Pacifica, just south of the San Francisco Bay area. Caltrans Devils Slide Tunnel project is an effort to bypass that slide and make the heavily traveled roadway safe for drivers and to eliminate the maintenance and traffic hassles caused by slope failures blocking the road. We first covered the project back in September of 2007 when the tunnel portion of the project commenced. In that post, you can find a Google Earth KML File showing the location of the tunnels and the new bridges associated with the project. In this post, Ill provide you with some updated progress information as well as some background on the geotechnical and other aspects of the project. More links and videos are at the end of the post. (Photo by Kim Komenich, San Francisco Chronicle).
Work started from the south portals in September of 2007. The tunneling methods being used is the New Australian Tunneling Method (NATM), and excavating is being performed by an Alpine 1 Road header (pictured at right, Photo by Kim Komenich of the San Francisco Chronicle) for the softer material, and conventional drill and blast for solid rock. In early March of this year, ABC7 News reported that the Northbound tunnel had been excavated to 181-m, and the Southbound tunnel to 90-m. The work continues around the clock.
At the North end of the project, there are two gracefully sweeping bridges over 1,000-ft long that connect the North tunnel portals with Highway 1 just South of Pacifica. In the last week or two, work on the bridges has reached about 95% completion. They constructed them from each side of the canyon, and met in the middle within 20mm. They are now performing the final deck pours and finishing work and expect to be done in July. One interesting aspect of the bridge is that the inside is hollow. They have included tubes for post-tensioning cables in the event that they find the bridge is sagging or something at a later date. Once the bridges are completed, the tunneling contractor will begin excavating from the North side as well to meet somewhere in the middle.
Miscellaneous Geotechnical Tidbits and Other Info
Alpine 1 Roadheader Custom for the project. Used for softer material.
Using fiber-reinforced shotcrete for the tunnel lining
No GPS underground of course, laser total station to control accuracy
Continuous LIDAR scans and photos of the tunnel as excavation progresses
3D Modeling from the LIDAR and imagery used to adjust tunnel design on the fly (first time this has been done)
Every 1.2 m, team must decide on what methods of support to use based on the type of material encountered
Another ABC7 News report from April of 2008. Covers some of the fancy technology behind the tunnel construction, including the use of total station surveying and 3D LIDAR scans of the tunnel that occur nearly continuously. Also includes 15 minutes of raw footage if youre interested.